Billing Methods

Audio: 

You use billing methods to determine how Oracle Projects generates bills for projects.

The following table shows the predefined billing methods in Oracle Projects:

  1. Cost/Cost - Accrues revenue and bills using the ratio of actual cost to budgeted cost (percent complete)
  2. Cost/Event -  Accrues revenue using the ratio of actual cost to budgeted cost (percent complete) and bills based on events
  3. Cost/Work -  Accrues revenue using the ratio of actual cost to budgeted cost (percent complete) and bills as work occurs
  4. Event/Event - Accrues revenue and bills based on events
  5. Event/Work -  Accrues revenue based on events and bills as work occurs
  6. Work/Event  - Accrues revenue as work occurs and bills based on events
  7. Work/Work - Accrues revenue and bills as work occurs