Costing Information
Burden Schedules
You must specify a cost burden schedule if you specify that a project type is burdened. The costing burden schedule defaults from the project type.

To enter Costing Burden Schedules, you must select and expand Burden Multipliers from the list of options in the Projects, Templates window.
- You can enter the following information in the Costing Burden Schedules window:
- Burden Schedule: Enter the burden schedule you want to use for this project or task.
- Burden Hierarchy: Enter the burden hierarchy you want to default to each burden schedule version.
- Fixed Date: Enter a fixed date for the burden schedule if you want all expenditure items to be burdened with the multipliers in effect as of that date.
Budgetary Control
You define budgetary controls in the Budget Integration window. Budgetary controls enable you to use a project cost budget to monitor and control project–related commitment transactions. You also use these controls to integrate project budgets with non–project budgets.
Budget Type
For Budgetary Controls: Select a project cost budget type. (Budgetary controls can be enabled for cost budget types only.)
For Bottom–Up Budget Integration: Select a project budget type to be integrated. You can select any active budget type.
Control Flag. Check the Control Flag check box if you want to enable budgetary controls for the budget type. (Budgetary controls can be enabled for only one budget type per project.)
Balance Type. This field is used to define top–down and bottom–up budget integration.
For Bottom–Up Budget Integration: Select Budget. Non–Project Budget. This field is used to define top–down and
bottom–up budget integration.
For Bottom–Up Budget Integration: Select a General Ledger budget from the list of values. The list of values displays defined budgets with a status of Open or Current.
Encumbrance Type. This field is used to define top–down and bottom–up budget integration.
Levels
Select a default control level for each budget level. When a baseline is created for the project budget, these control levels are used as default values for each budget level:
• Project
• Tasks
• Resource Groups. Select Default from Resource List if you have defined default control levels for your resource list.
• Resources. Select Default from Resource List if you have defined default control levels for your resource list.
Time Phase
The system uses these values to calculate available funds.
• Amount Type. Select an Amount Type to determine the beginning budget period.
• Boundary Code. Select a Boundary Code to determine the ending budget period.
For more information about defining control levels and time phases (also referred to as time intervals) for budgetary controls